UNITED NATIONS DEVELOPMENT PROGRAMME
Project
of the Government of the Islamic Republic of Pakistan
![]()
PROJECT
DOCUMENT
|
Project number: |
PAK 93/'006/A/01/99 |
|
Project title: |
Kasur Tannery, Pollution Control (KTPC) |
|
Duration of Phase 1: |
One year and six months (Phase 1) |
|
ACC/UNDP sector and sub-sector: |
Health 1000, Environmental Health 1030 |
|
Government sector and sub-sector: |
Leather & Leather Products Industry |
|
National executing agency: |
Housing. Physical and Environmental Planning Department (HP&EP) |
|
Government
Implementing Agency |
Kasur Development
Authority (KDA) Government of Punjab through Kasur Tannery Waste Management
Agency (KTWMA) |
|
Implementing agency for technical |
United Nations Industrial Development Organisation |
|
assistance: |
(UNIIDO) |
|
Estimated starting date: |
January, 1996 |
|
National inputs in millions of Rupees |
Government of Pakistan, Export Development Fund (EDF) Rs. 80m-, Economic Affairs Division (EAD) Rs. 13m-, Government of Punjab Rs. 86-m- Tanneries Association Dingarh (TAD) Rs. 20m. Total; local inputs: Rs. 199m not including contribution in kind. |
|
UNDP financing (Phase 1): |
IPF: US $1.218,800 TSS2: US $78,500 AOS: US $99,352 |
Brief Description: The project, through the Kasur
Environmental Improvement Programme (KEIP) framework, intends to contain and
reduce the environmental deterioration caused by tannery waste, to improve the
tanners existing inadequate technical and managerial skills in tanning
operations, to promote environmental awareness among the population, thus
improving the overall living and working conditions and creating an
environmentally sustainable development of the tanning industry in Kasur. The
project also includes various measures to build and strengthen necessary
institutional capacities and regulatory measures as well as to develop
necessary actions for implementation of the remainder K-EIP. For optimum
results the KTPC project "ill be implemented in phases. Phase I is focused
on introduction of better process control in tanneries, tanneries in-house
pretreatment and establishment of the overall drainage system including
evacuation of the existing stagnant pools.
TABLE
OF CO.NTENTS
Part A. Context
A. I Country Background
A.2 The leather industry in
Pakistan
A.3 National policy on the
environment
A.4 Kasur's Geographical
Background
A.5 The tanning industry in
Kasur
Part B. Project
Justification.................................................................................................5
B. I Present situation
B.2 Expected end of project
situation.
B.3 Project target
beneficiaries and impacts
B.4 Project financial
viability.
B.5 Project strategy,
institutional and financial arrangements
B.6 Reasons for assistance
from UNDP
Part C. Project
development objective
.............................................................................11
Part D. Immediate
Objectives, outputs and activities
.................................................……11
Part E. Project inputs
.........................................................................................................18
Part F. Risks and
safeguarding actions
.........................................................................21
Part G. Prior
obligations, prerequisites and other undertakings
.............................22
Part H. Project review,
reporting and evaluation
..........................................................24
Part 1. Legal context
...........................................................................................................25
Part J.
Budgets.....................................................................................................................26
[Budget Sheets Phase I and
Phase 11 (tentative) attached]
Annexes:
Annex I Map of Tannery
Clusters Area
Annex 11 Project Impacts
and benefits
Annex III Kasur
Environmental Improvement Programme (KEIP)/Project Implementation Schedule/Work
Plan
Annex IV Technical Project
Data and Costs
Annex V Letter of Agreement
between Government of Pakistan and UNIDO as implementing Agency
Annex VI Organization
Structure (KDA/KTWMA)
Annex VII Land Acquisition
and Permits
Annex VIII Schedule of
Funding
Annex IX Draft Terms of
Reference/Job Description for Technical Assistance
Annex X Review of Environmental
Issues
Annex XI Monitoring
Indicators and Arrangements
![]()
Part A. - Context
A.I. Country
Background
Pakistan is
administratively subdivided into four provinces: Punjab, Sindh. Northwest
Frontier Province (NW'FP) and Baluchistan, as well as the Federally
Administered Tribal Areas (FATA). The mid-1994 population is estimated at about
128 million people, growing at about 2.9 per cent per annum.
As an indicator of poverty,
40 % of households received only I 8 % of total income (I 994-85). Only 37 % of
the adult population were literate in 1994. This is below the average of 42 %
for South Asia and 60 % for third world countries. Availability of health
services is limited to 55 % of the population, safe water to 45 % and
sanitation to 20% of the population (1985-88, UNDP Balanced Development Report,
1992 p.2). With its human development indicators, Pakistan ranks 120th
out of 160 countries and clearly falls in the low human development category.
Pakistan's per capita GNP
was $430 in 1993 - approximately on a par with China, above India and
Bangladesh and below the Philippines and Indonesia. Pakistan's per capita GDP
was $460 in 1993, of which 25 % was contributed by agriculture (including
forestry and fishing), 25 % by industry and 50% by utilities, construction,
trade and services.
In 1991-92, about 47 % of
the employed labor force were working in agriculture (including forestry. and
fishing) as against 24 % in industry (including mining and quarrying), and 29 %
in utilities, construction and trade.
Pakistan's economic
performance has been impressive during the last decade. The GNP growth rate has
averaged 6 per cent. Agricultural production has increased at the rate of 4,3
per cent, while the manufacturing sector has expanded annually by 7,2 per cent.
Per capita income has increased by over 2 per cent per annum and the proportion
of households below the poverty line has declined.
The economic performance of
Pakistan has not been achieved without producing significant social distortions
and considerable damage to the environment. Consequently, a number of
infrastructural bottlenecks have emerged especially in power, transport and
communications. Municipal investments have also lagged behind and the quality
of service provision has declined. This adversely affected the quality of life
in the urban areas. Levels of pollution, congestion, crime and violence have
increased in most of the metropolitan cities. Simultaneously, there has been
little improvement in social indicators like the literacy rate, infant
mortality rate and life expectancy.
A.2. The leather
industry in Pakistan
According to a survey
conducted by LIDO (1994), there are about 595 tanneries in Pakistan, most of
them located in clusters or industrial zones in Karachi, Lahore, Kasur, Multan,
Faisalabad, Peshawar, Gujranwala and Sialkot. While traditional, small and
medium-scale units still prevail, there are some large, well-mechanized, export
oriented tanneries, especially in Karachi.
The raw material base for
the expanding leather and leather based producing industry is drawn from a
livestock population consisting of 17.4 million cattle, 14.7 million buffaloes,
29.2 million sheep, 35.4 million goats and 4.5 million horses, camels
and donkeys, producing about 5.8 million of cattle hides and over 35
million of goat and sheep skins a year.
The rawhides and skins
collection and conservation in Pakistan is partly handled through organized
sector slaughterhouses and partly through collection by private collectors
after slaughter in villages and after religious festivals. The hides and skins
have good quality, but are partly downgraded through poor flaying and curing
practices.
Despite this large
livestock base, the country has turned from a net exporter (which it was only a
few years ago) into a net importer of hides and skins. This change is a result
of a combination of bans, restrictions and/or levies on exports of raw and
semi-processed hides and skins and various incentives for exports of higher level of processing products with higher added value.
The leather and leather
products sector now represents one of the most important industrial sectors,
significantly contributing to the national economy: in 1989-1990 sector exports
amounted to Rs. 6 billion for semi-processed and finished leather (over 52% of
total sector exports), Rs. 3.4 billion for leather garments, Rs. 1.9 billion
for different leather products (gloves, footballs, leather goods) and Rs. 0. I
billion for leather footwear, for a grand total of Rs. 1 1.5 billion. In
1990-91 this figure had increased to Rs. 16.7 billion. With a share of II per
cent in total export earnings, the leather and leather products is second only
to cotton textiles in this respect. In 1993-94, the exports of the leather
sector touched US$770 million.
It is estimated that this
sector directly employs more than 200,000 workers and if the cottage sector is
included ,it is believed that over one million people depend for their
livelihood on this sector . The downstream processing, i.e. the leather
products sub-sector is labor-intensive and has potential for female employment.
There is, however, a
growing concern that the expansion of the leather sector has resulted in
considerable environmental degradation and that local processing of both
domestic and imported hides and skids has brought pollution which used to take
place elsewhere. While the 8th Five Year Plan (1993-1998) for Pakistan
envisages continued industrial development of the country by more investment in
industries which would bring higher export value, enhance efficiency,
productivity, quality of products and promote labor intensive industries, it is
also provided that industrial growth needs to be ecologically sustainable in
the long run and that the associated pollution which has been and still is the
major problem of the tanning industry needs to be controlled by optimum use of
chemicals, recycling, treatment and better utilization of liquid and solid
wastes.
Environmental pollution in
several tannery areas has reached such proportions that it represents a direct
health hazard to the population, and in particular to water supplies for
different purposes. Urgent remedial actions are required to reduce the negative
impacts on the environment.
On the other hand,
disruption in the activities of this industry and thereby in the production of
leather and of leather products, would have a grave impact on export earnings,
on employment and on the utilization of available natural resources.
A.3. National policy
on the environment
Pakistan is not a major
polluting country on the global scale nor a large consumer of resources.
However, the country's environment is in a state of acute degradation and
misuse.
Although the 1973
Constitution gave responsibility for environmental pollution control and
ecology to the Federal and Provincial Governments, there was very little
environmental input in national planning throughout the 1970s.
Environmental legislation
is dominated by the Pakistan Environmental Protection Ordinance 1983 (PEPO).
'Me PEPO is essentially an anti-industrial pollution ordinance, which enables
both Federal and Provincial legislatures to enforce control, although little
such action appears to have taken place. Although pollution regulations and
standards have been proposed, none have yet been adopted. Therefore, this
aspect of PEPO remains largely unimplemented. In the absence of regulations and
their enforcement, industries and municipalities continue to pollute public
waters.
There are a number of other
Acts, Ordinances and Codes covering sectors, such as agriculture (1971),
forestry (1927), wildlife (1974), cultural resources, motor vehicles (1965) and
factories (1934) (the last two including some provisions controlling air
pollution, which, however are poorly enforced).
The 1984 Factory Act
contains provisions for controlling the discharge of industrial effluent on
land into the air and water. This Act is not enforced. A survey in 1985
showed that only 3% of industrial plants across the country treated their waste
to international standards and the Factory Act standards.
Both public and
governmental concerns and awareness of Pakistan's environmental problems are
spreading. Following a three-year long extensive consultative process a
National Conservation Strategy (NCS) was approved on I March 1992 by the
Cabinet of Pakistan. The NCS provides a broad framework for addressing
environmental concerns in the country. The main environmental problems
identified In the NCS includes, among others, the lack of supportive frameworks
of regulations as well as institutional and financial mechanism which is
aggravated by inadequate systems for the disposal of industrial and municipal
waste and a high level of water and air pollution. Greater responsibilities and
initiatives in addressing environmental problems have been delegated to
provincial and lower authorities as well as to the private sector and NGOs,
etc.
The 8th Five Year Plan
recognizes the need for environmental conservation and accepts that the
environment is the major issue. Under the 8th five year plan , the
Government envisages to allocate 1% of GNP to support the pollution -control
and environmental protection activities put for-ward in the NCS.
The Implementation Plan for
the NCS lists the project as a priority activity. The Government wishes that
the project be implemented as a model for nationwide efforts to deal with
industrial effluents.
A.4. Kasur's Geographical Background
The town of Kasur is
situated about 55 km southeast of Lahore, in the province of Punjab, near the
border with India, where the river Sutlej enters Pakistan. Kasur has been known
since antiquity as a centre of trade, commerce and culture. According to the last
(I 98 1) census the number of inhabitants was about 155.500. For 1993 it is
estimated to be about 270.000.
The municipal boundary
covers an area of about 2,335 acres, surrounded by agricultural land (wheat,
grams, maize, rice and cotton). Mainly due to tannery effluent water, large
land areas are at present under water constituting the so called stagnant lakes
or pools, for which the town has become famous during the last few years as one
of the most heavily polluted towns in Pakistan.
The textile industry is the
largest industry in Kasur in terms of employment, followed by the tanning
industry. These industries dominate the town, with a large proportion of the
population directly or indirectly depending on them.
Kasur, located in a NW-SE
ridge is surrounded by a flat landscape. The land is characterized by low
permeability of the topsoil. Wind erosion and water logging deteriorates soil
qualities thereby reducing land areas suited for agriculture. Farming relies on
irrigation, using ground water and private tube wells. Intensive irrigation has
changed the soil structure. Waterlogging and high salinity decrease the
productivity of the agriculture sector. A Salinity Control and Reclamation
Programme (SCARP) consisting of 12 wells and drainage channel, Pandoki Outfall,
has been constructed in order to overcome these disadvantages. However, only
one of these wells is currently in operation.
The Kasur district covers a
gross area of 981,702 acres of which 705,224 acres is classified as cultivable
land. Under irrigated agriculture condition, the soil is very productive. Rice,
sugarcane, cotton, various fodder, maize and vegetables are the main crops in
summer, while wheat is the only dominant crop in winter (rabbi).
A former river, Rohi Nullah,
is meandering through the town. Natural affluent to this river has been cut off
and today the water in the river consists of the domestic sewage from the town
and some of the wastewater from the tanning industry. The riverbed is also the
dumping site for garbage and other solid wastes. Farmers along the river are
using the mixed sewage for irrigation, watering of buffaloes and washing of
clothes.
Rohi Nullah
disappears in a semiarid area near the Pandoki Outfall. During the monsoon
period (July and August) the river fills up the former bed and even submerges
the downtown areas of Kasur. In this period of the year the river also reaches
the Pandoki Outfall and finally the Sutlej River, one of the main tributaries
of Indus.
Yearly rainfall is about
500 mm and yearly evaporation is about 1,500 mm, i.e. a deficit of 1,000 MM.
A.5. The tanning
industry in Kasur
Tanning has a longstanding
tradition in Kasur. Initially, rather primitive tanneries, in which all
operations were carried out annually, and in which tree barks for tanning
proper were used, had apparently been established in the Dingarb area on the
bank of the Rohi Nullah.
Subsequently, tanneries
started spreading over a wider area south of the river and Kot Molvi, Abdul
Qadir Niaz Nagar and Yonus Nagar agglomerations were gradually developed. With
its 170 tanneries, Kasur is the biggest tanning concentration in number
in the country. The map giving the general layout of the tannery clusters in
Kasur is given in Annex I.
According to data provided
by the Tanneries Association Dingarb, Kasur, the average daily input of
all tanneries in Kasur is estimated to be over 190 tons of wet salted weight,
comprising some 8,000 hides (cattle, buffaloes), and between 12,000 and 15,000
skins (sheep and goats) per day.
The small-scale units
mainly produce hides and/or skins up to the wet-blue stage only, as they do not
have the facilities for the finishing of leather. They sell the semi-processed
leather to tanneries in Karachi, Sialkot and other places, where the leather is
finished for various end uses. Some of the small and medium-sized tanneries
also produce vegetable tanned leather for sole leather and for other purposes.
The traditional pattern has
been well preserved: except for 3-5 larger and mechanized tanneries with a more
or less industrial way of production, the other tanneries are small, family
owned units, employing up to ten workers. Traditional family owned tanneries
typical of Kasur are very basic. Most operations are still carried out with
very limited use of machines and equipment. Chrome tanning has, to a great
extent, replaced the slow vegetable tanning process but the ancient bag-tanning
method can still be seen. Some tanners still prepare their own chrome liquors
from dichromate under poorly controlled conditions. Due to the unavailability
of water supply that is encouraged by its econon3ic incentives, all the
tanneries are presently using the underground water for their tanning
activities.
Most of medium-sized
tanneries finish their chrome-tanned leather using only water based coatings
and hand-spraying techniques. The largest tannery has fully automated spraying
units (two) for the finishing of the leathers produced and several of the other
larger tanneries are in the process of installing automated spraying units as
well.
In contrast to the export
oriented tanners of the Korangi industrial zone of Karachi, who operate large,
well equipped factories, Kasur has remained a hide processing centre, mostly
catering to the needs of the local, low-price bracket leather footwear manufacturers.
Profit margins are low and access to capital and potential for modernization is
limited. Many will find it difficult to survive in the increasingly competitive
environment.
In view of its proximity to
the large market of Lahore and the availability of leather and cheap labor in
Kasur, it is somewhat surprising that no downstream manufacturing units
(footwear, leather goods) have been established in Kasur itself, they remain
within the Lahore area.
Sanitary conditions both
within and outside tanneries are bad by any standard: few units are kept tidy.
However, possibly due to the UNDP/UNIDO preparatory assistance project, an
increasing awareness of the negative impact of tannery operations on the
environment has been created among members of the tanning community.
Little attention is given
to occupational health standards, protection from exposure to harmful chemicals
and to safety at the work place.
The well organized
Tanneries Association Dingarh, Kasur is the main driving force behind endeavor to
catch up with more advanced tanners in the country and, in particular, to resolve the problem of treatment and discharge of
tannery effluent which, sooner or later. is bound to paralyse the tanning
operations in Kasur.
B. Project
Justification
B. 1. Present
situation
Kasur has been suffering
from an environmental degradation, not only to air, surface water, fertile land
and groundwater, but also a direct health hazard to the people living and
working the affected areas as a result of: 9,000 cubic meters of heavily
polluted tannery waste water from the three tannery clusters per day. About
2,500 cubic meters of the above tannery effluent together with domestic sewage
is discharged into the Rohi Nullah. This is used for irrigation in the
down stream parts of Rohi Nullah. The remaining ampount is discharged to
the stagnant pools permanently covering an area of 327 acres and another 311
acres during the monsoon period. The chemically polluted water adversely
affects the growth of crops, plants and crop yields outputs from animals and
their health, in addition to contributing to social problems in the area.
A total of 100-150
tones/day of solid wastes and 150-200 tones/day of solid domestic waste is
disposed of by casual dumping at various places, including the Rohi Nullah.
Water supplies from hand
pumps and tube wells, and foodstuffs produced in the area are contained with
dissolved solids, especially sodium chloride and sulfides. The Environmental
Impact Assessment (EIA) (IUCN, February 1993, page 26) attributes the
groundwater contamination to the tannery effluent, wastewater and stagnant
pools.
Improper use and handling
of chemicals has rendered workers and residents to hazardous exposures.
Respiratory disorders, lung infection related diseases, diarrhea/dysentery and
typhoid are the most serious illnesses among the community population etc.
Currently 50,000 to 60,000 people are exposed to the environmentally polluted
conditions. Most of the tanneries are small and their owners have limited
knowledge of simple methods and ways of improving their tanning process, and
working situation.
The following is the amount
of the tannery pollution load discharged (per annum): 4,000 tones of BOD;
11.000 tones of COD2; 10,000 tones of SS; 160 tones of Chromium; and 400 tones
of Sulfide (Calculated on basis of 13,000 m3/d; 300 days per year). It should
be noted that although being a primary treatment type, the proposed treatment
plant is expected to eliminate 65 % of the above BOD; 55 % of the COD; 95 % of
the suspended solids; 95 % of the chromium; and 98% of the sulfide.
Deficiencies in providing
urban services to Kasur Township, thus leading to and worsening the existing
polluted situation.
1 Abbreviation for biochemical oxygen demand.
2 Abbreviation for
chemical oxygen demand.
3 Solids in suspension
in waste water and effluent.
B.2. Expected
end-of-project situation
It is expected that the end
of the project situation in Kasur, with respect to environmental protection
measures will be as follows:
The
outfall sewer, 'Final outfall channel or the Green Channel', to Pandouki
Outfall constructed and in operation;
The
stagnant pools dried out and ready for reclamation;
The
in-house (within the individual tanneries) pre-treatment arrangements (installation
of coarse screens and simple grease chambers, and process water flow meters)
finalized and in operation;
The
industrial and sanitary waste water pollution system in tannery clusters
rehabilitated/constructed and in operation;
The
Common Tannery Effluent Primary Treatment Plant with control lab-oratory
installed and in continuous operation;
The
CEPTP's sludge processing, transport and disposal facilities are operational
(including disposal of tannery solid wastes);
The
Authority (KDA) and Agency (KTWMA) responsible for the engagement of the
treatment plant including solid waste and sludge handling, personnel and
economy, well established for smooth operation of the project activities.
Lessons from experience in the formulation, management and coordination of
project will be applied, in other environmental pollution control activities in
other parts of the country;
Sufficient
number of local staff, employed by KTVIMA, well trained to independently
operate and maintain the CEPTP with all auxiliary facilities including sludge
handling and disposal system; leading experts and consultants trained to use
the knowledge gained in dealing with similar problems elsewhere in the country;
The
chrome-recovery plant, ideally potentially usable as by-products pilot plant,
installed and in operation;
Local
tanners are well acquainted with cleaner, environmentally friendly leather
processing methods. Some of the methods, adapted to the local conditions,
actually accepted for the production of various types of leather in day-to-day
work;
Considerable
improved general awareness concerning occupational health hazards, industrial
safety and hygiene and specific measures adopted and adhered to;
Kasur
Municipality Committee will be strengthened institutionally so that it can
effectively assume its assigned functions;
Specific
details required for urban development of Kasur, for implementation of the
remainder of the Kasur Environmental Integrated Programme as well as other
social impact related (women, children and health monitoring) studies will be
available for the necessary follow-up actions.
Sound
systems/mechanism facilitating 'polluters pay' principles will be established.
The pollution load
presented in Part B. I above will be reduced and sanitarily disposed as follows:
|
Suspended Solids |
95% |
|
C. 0. D. |
55% |
|
B. 0. D. |
65% |
|
Sulfide |
98% |
|
Chromium |
95% |
B.3. Project target beneficiaries and
impacts
The following target beneficiaries of the
project have been identified:
- About 170 tannery owners benefit directly
in the sense that the project will enable the continuation of their activities
on a sustainable basis, which otherwise might have been curtailed for
environmental reasons they will also benefit economically because they will
initially pay part of the cost if pollution abatement, with the remainder being
financed by various government agencies.
- An estimated 1,600
tannery workers will obtain the direct benefits of cleaner, safer and healthier
working conditions; this will also apply to the large number of casual workers,
transport operators and other workers in one way or other associated with the
tanneries operation.
- The surrounding
community, particularly residents in the tannery clusters themselves, will also
obtain health benefits from the improvement of the environment in the area, as
will the farmers using the improved water quality in Rohi Nullah for
irrigation purposes; the EIA study estimated that a total of about 50,000 to
60,000 people are currently at risk.
- Local public
agencies such as Municipal Committee of Kasur, the Housing and Physical
Planning Department as well as other environmental monitoring and policy making
bodies will benefit directly or indirectly from the project.
- An estimated 1,000 landowners,
mostly small farmers, will benefit from reclaiming the stagnant pools now
permanently submerging about 132 ha (or 327 acres) of land, and adversely
affecting crops during part of the year on another 126 ha (or 311 acres) of
land.'
A more detailed analysis of
the expected environmental, policy, poverty, health impacts as well as economic
benefits as a result of the project is provided in Annex 11. A summary of the
project envisaged impacts according to the Government of Netherlands impact
checklist is also attached to Annex 11.
B.4. Project financial viability.
In view of the pilot nature of the project,
all capital expenditure towards implementation of the project facilities is to
be financed as a grant to the Government. KTWMB through KTVFMA will have to
finance 0 & M and capital depreciation costs out of contributions from the
tanners, Municipal Committee of Kasur, the District Council and Government of
Punjab.
According to the
technical-economic Study completed under the UNDPIUNIDO Preparatory Assistance
Project DPIPAK/89/025 estimates of the annual recurrent costs of the project
including maintenance and depreciation are as follows:
Status early 1993; in the meantime the
inundated and affected areas considerably increased.
|
- 0 & M costs: |
Rs. 13-96 million or US$ 536.923 ( 63.7%) |
|
- Depreciation: |
Rs. 7.94 million or US$ 305,384 ( 36.3%) |
|
Total: |
Rs. 21.90 million or US$ 842,307 (100.0%) |
The above annual recurrent
cost represents less than I% of the sales value and about 2.5 % of the
value-added generated by the leather industry in Kasur. Furthermore, the above
Technical-Economic Study identifies the treatment system in the project as the only
available least cost solution.
The following sharing
formula to meet these annual 0 & M and depreciation costs has been agreed
upon between Government of Punjab and the Tanneries Association Dtngarh, Kasur
which needs to be laid down in a separate legal agreement:
|
- Kasur tanners |
50% (or Rs. 10.95 million on current estimates) |
|
- MCK |
15 % (or Rs. 3.29 |
|
- District Council |
15 % (or Rs. 3.29 ' ' . . ) |
|
- Government of Punjab |
20% (or Rs. 4.38 on account of depreciation only) |
The Finance Department,
Government of Punjab, which will open a Depreciation Fund within the Public
Account, from which replacement investments would be financed, will keep
contributions towards depreciation.
In order to further ensure
the project financial viability as the depreciation figures are based on
historic costs, the Government of Punjab agrees that the above percentage
sharing formula is maintained at variation of 0 & M costs and subject to
the adjustment to depreciation. Depreciation costs will be based on
periodically (every 2 years) revalued asset value based on replacement costs.
For the same reason, the real value of the accumulated Fund balance that is
maintained from the outset should earn a return at least equal to the increases
in price of the assets for which the fund is ultimately to provide replacement.
The Government of Punjab agrees to formalize above arrangements in the legal
agreement before the start of the project.
B.5. Project strategy, institutional
and financial arrangements:
a) Project approach
The Kasur Tannery Pollution
Control Project (KTPCP) is the first part of the mom broadly conceived Kasur
Environmental Improvement Programme (KEIP), details of which are presented in
Annex 'M. KTPCP comprises those programme elements which are:
i) Institutional
strengthening actions to facilitate project and programme implementation and
sustainability-I
ii) Implementation of
components that are ready for implementation and also respond to urgent
environmental upgrading needs;
iii) Preparatory support
actions to prepare/finalize subsequent stages of KEIP development;
For practical reasons and
to achieve optimum results, technical assistance to be provided with LTNDP
funding will be in phases, budget allocations for and implementation of which
will be linked to appropriately match the availability of national inputs,
actual progress of work at the project site and actions taken to ensure project
sustainability.
The Government, on the
other hand, is committed to not only the implementation of KTPCP, but also an
early follow-up implementation of the remainder of KEIP.
b) Selection of technical alternatives
The technical solution
selected as the best option for the project is a result of an extensive
technical-economics study of the Preparatory Assistance under which various
solutions were analyzed from technical and economic consideration. Other
technical treatment alternatives are rejected due to their high cost involved.
The selected treatment method is a simple, cost effective alternative, adapted
to specific local conditions.
A possible alternative to
the problem is to establish individual treatment plants for each of the
existing tanneries. However, in view of the closeness of the units to each
others and due to lack of sufficient space for setting up and operation of
these individual plants, it would b-e technically impossible to opt for this
alternative and furthermore, this alternative would be too costly.
c) Implementation strategy
Detailed designs and
outline tender documents have been prepared in the technical-economic study of
the preparatory assessment phase. The detailed design documents and bills will
require some modifications as a result of the change in solid waste disposal
site, as well as changes in the built-up area of the tannery clusters
necessitating some minor changes in the lay-out of pumping stations.
Additionally, unit costs will be reassessed prior to bidding in view of price
escalations taking place. Hence, a final design review is required early on
during project implementation before tenders can be called. Technical
assistance in the form of consultants and subcontractor services is provided
for in the project.
Contracts for civil works
would be let by KDAIKTNVMA through local competitive bidding. In order to speed
up the implementation of the project and to avoid significant price increases,
the civil works will be split into five smaller packages, thus enabling smaller
local companies to enter the bidding. The tender will therefore have to be
split in to the following different packages accordingly:
|
- Drainage in tannery clusters |
(equiv. about US $350,000) |
|
- Solid waste site plus lagoons |
(equiv. about US $1,100,000) |
|
- Treatment structure |
(equiv. about US $1,300,000) |
|
- Pump houses in clusters |
(equiv. about US $120,000) |
|
- Final outfall |
(equiv. about US $1,500,000) |
An outline of the Technical
Project Data and costs is given in Annex IV. It is foreseen that physical
implementation of major civil works contracts would commence by early 1996 and
would be completed by the beginning/mid-1997and that delivery and installation
of equipment would take place during 1997, while introduction of cleaner
technology including establishment of the chrome recovery, by-products plant
and related training activities start from October 1995 (an outline of major
project schedule and tentative project work plan is in Annex 111).
The technical assistance
will only be provided after the project approval has been accorded and
envisaged prerequisites and preconditions have been made available and/or
fulfilled.
UNIDO agrees to provide
technical backstopping support services related to introduction of low waste
technologies including chrome recovery/byproducts, technical evaluation of
equipment and training, as identified in the TSS2 project budget and as
required during the project duration (Annex V refers). Its services, in
particular, do not include the overall project management and all construction
works except guidance in the initial review and introducing minor modifications
of designs made during the project of preparatory assistance.
d. Institutional arrangements:
The Housing, Physical and Environmental
Planning Department (HP & EP) of the Government of Punjab is
administratively responsible for provincial policies and programmes in the
areas of environmental planning and enforcement of standards,
physical/urban planning and the provision of water and sanitation
services. As such HP & EP has administrative control of its two subsidiary
agencies, i.e., the Public Health Engineering Department (PHED) and the
Environmental Protection Agency (EPA). Considering its functions and
responsibilities, commitments, willingness to the project and in order to
enhance the Government ownership of the project as well as its responsibilities
for the achievement of objectives and sustainability of the project, HP &
EP will be the executing agency for the project.
In its capacity of the
national executing agency HP & EP will appoint a National Project Director
(NPD) who will be responsible for overall project development and liaison with
concerned government agencies and UNDP/UNIDO and with possible donor(s). In his
work he will, during project life, be assisted by the Assistant National
Project Director financed from the UNDP technical assistance project budget.
HP & EP, acting through
the Kasur Development Authority (KDA) established as a legal authority to set
up, guide and supervise the Kasur Waste Management Agency (KWMA) for
construction, operation and maintenance of the Common Effluent Treatment Plant
(CEPTP) will delegate the handling of all project related matters to the Kasur
Tannery Waste Management Agency (KTWMA). This will enable KTWMA to assume
ownership of the project.
Therefore, the KTWMA,
acting through its Project Director, assisted by the technical, administrative
and auxiliary staff will be the leading project implementation agency.
The KTMA will also ,among
other duties, be responsible for revenue collection from the tanners.
The KTWMA as the key
project-implementing agency will be responsible for the implementation of the
civil works under the project through competitive bidding on a deposit basis on
behalf of KDA/KTMA.
KTMA will delegate the
direct responsibility for the promotion of in-house tannery technology
improvements, operation improvements and the recovery and by-products pilot
plant to the Kasur Tannery Association (KTA). The KTA will submit a detailed
organization and operational plan of action to the Agency in this regard.
UNIDO is agreed to be
another implementing agency responsible for delivery of inputs as specified in
the main project budget document (i.e. specifically excluding overall
coordination and construction works).
A Steering Committee will
be established to oversee project implementation, chaired by the Chairman,
Planning and Development Board, Government of Punjab, comprising
representatives of Government of Punjab, KDA, KTWMA, UNDP, UNIDO, and possible
donors.
Other functions,
organizational structure and staff requirements of the KDA and KTMA are
provided in Annex VI.
e. Financial arrangements:
The project will be launched
with funding by the Government of Pakistan and UNDP; however, every effort will
be made to persuade other donors earlier interested in supporting the project
to reconsider their decision.
The amounts originally
proposed were as follows:
|
UNDP |
US$ 2.50 million |
|
Netherlands |
US$ 3. 10 million |
|
NORAD |
US$ 1.25 million |
In that case, for reasons
of efficiency in project implementation, it is expected that Netherlands and
NORAD will make their contributions by way of cost sharing to UNDP. Agreement
on the exact contributions of each donor, their modality and schedule etc. would
be prepared according to usual procedure.
Accounting and financial
reporting procedure will be followed according to UNDP guidelines under the PPM
section 30503. Furthermore, in order to facilitate the project operation, the
National Project Director is agreed to approve all payments from the project
accounts and will be responsible to the KTWMA and HP & EP for record
keeping, aggregation of documents, reconciliation of bank statements as
required, and preparation of applications for replenishment.
Financial and accounting
arrangements between UNDP and UNIDO will be made in accordance with the
Standard letter of Agreement between the Government and UNIDO as implementing
agency in Annex V.
B.6. Reasons for
assistance from UNDP
The project is considered
priority one in the action plan for the implementation of the National
Conservation Strategy. Addressing environmental pollution problems especially
identified under the NCS plan is one of the four priority areas in the UNDP and
Government 5th Country Programme (1993-1998).
Furthermore, there has been
considerable multilateral and bilateral assistance in the leather sector during
the past decades. The external assistance has concentrated in the fields of
institutional strengthening, training and extension services, improvement of
quality and increased productivity, improved leather finishing etc.
C. Project development objective
The development objective of the project is
to control the indiscriminate discharge of potentially harmful solid waste and
heavily polluted waste waters and improve the working and living conditions in
Kasur, thus ensuring an environmentally sustainable social and economic
development of the area. Achievement of the project objectives will also
contribute to a successful implementation of the National Conservation
Strategy.
D. Immediate Objectives, outputs and
activities
1. Immediate objective 1
Containment of environmental degradation
caused by the indiscriminate discharge of toxic effluents by Kasur tanning
industry and creation of cost-effective infrastructure for improvement of
overall working and living conditions in Kasur.
1. 1 Output I
Evacuation of the stagnant pools or tannery
effluents and the land ready for reclamation.
Main activities for output 1.
1.1.1 Finalization of design details,
drawings and tender documents; tendering process, evaluation and awarding etc.
1.1.2 Construction of a
final outfall drain (or the 'Green Channel' of about 8.4 km length) for taking
the treated effluent from the pre-treatment plant to the Pandoki Outfall drain,
from where it WW discharge into a branch of the Sutlej River.
1.1.3 Construction of an
interception channel along the 'stagnant pool No I' to prevent further inflow
of storm water into this largest stagnant pool area. The channel will be
connected with the final outfall drain for carrying away the storm water.
1.1.4 Coordination with
other construction works under the project ensuring the inflow of tannery
effluents to the pools will be conducted to the common effluent treatment plant
for treatment before discharging into the final outfall drain.
1. 1.5 Continuous
supervision of the natural evaporation (estimated at 1,000 min to 1,50 mm per
year) of the accumulated waste water in the stagnant pools ensuring that
the land areas will be ready for reclamation and further use in accordance with
the future town planning.
1.2 Output 2
Establishment and operation of a tannery
effluent drainage and collection system within the three main tannery areas of
Kasur.
Main activities for output 2.
1.2.1 Finalization of design details,
drawings and tender documents; tendering process, evaluation and awarding etc.
1.2.2 Rehabilitation and
extension of the Dingarb sewer lines. Since the establishment of a proper sewer
system According to sound hydraulic principles has to be done in combination
with 'in house arrangements' in the tanneries themselves, detailed design of
the works under this activity heading will be finalized during project
implementation.
1.2.3 Constructions of a
collector channel close to Robi Nullah and of a pumping station. Through
this collector channel effluent will flow by gravity to the pumping station
from where it will be pumped over the ridge to the Pucca Drain.
1.2.4 Rehabilitation and
prolongation of the Pucca Drain to the cluster of tanneries. All tannery
wastewater including from Dingarh cluster will flow by gravity to the
pre-treatment works.
1.2.5 Development of a
drainage plan for two clusters namely Kot-Abdul and Niaz Nagar so as to guide
the tanners of proper operation and maintenance of their sewer system in their
existing self help scheme. This is expected to reduce the current maintenance
costs and ensure better flows of effluent, thus preventing settling of solids
or blockage in the sewers.
1.2.6 Construction of a
central collector drain and a pumping station for Younus Nagar cluster, pumping
the wastewater into the Pucca Drain.
1.3 Output 3.
Establishment and operation of a common tannery
effluent treatment plant (CEFRP) including a simple analytical laboratory with
local staff well trained in their operation and maintenance of the plant.
The plant is designed for
treatment of a total effluent volume of 13,000 m3/day including 20 % of
sanitary wastewater which is set at year 2007. The proposed treatment system
consists of screening, vertical sedimentation and biological purification in a
naturally aerated lagoon system with a retention time of over four days. To
avoid shock-loads and obtain a more homogeneous quality of wastewater, which is
better for the biological process, equalizing tanks with a retention time of 24
hours have been incorporated in the design. The expected elimination of
pollutants is as follows:
Solids 95%
C.O.D 55%
B.O.D 65%
Sulfide 98%
Chromium 95 %
The simple analytical
laboratory at the CEPTP site is for the purpose of monitoring effluent
characteristics and parameters, thus optimizing the plant performance. It will
also analyze and monitor the groundwater status at the site for the treatment
plant, along Pandouki Outfall, and around at the landfill area etc. The data
stored and processed in a computer unit (PC with appropriate software) will
also serve the laboratory and the tanners as a data bank on low-waste leather
and treatment technology.
Main activities for
output 3.
1.3.1 Finalization of
detailed designs including structural design and drawings for the civil works
and equipment and tender documents; tendering process, tender evaluation and
awarding, equipment requisition etc. (During the finalization of detailed
designs for implementation of activities under this output, consideration will
be given to the introduction of artificial aeration by means of surface
aerators at a later stage in order to solve the anaerobic odor problem as well
as to increase the overall efficiency of the plant.)
1.3.2 Installation of
coarse screens and simple grit/grease chambers in every tannery to protect the
sewer system from clogging by coarse floating or "settled" matters.
Erection of small-sized tanks within each tannery in order to reclaim part of
the sludge as well as for installation of four tanks within the tanning area to
reduce the BOD concentration load before the effluent is lead to the treatment
plant is also foreseen.
1.3.3 Carry out civil
construction works for CEPTP including the laboratory and a main control and
project building at the disused railway track near 'Stagnant Pool' No.2.
1.3.4 Supervision to the
national contractors) executing the construction works on the plant and other
related components.
1.3.5 Installation,
acceptance test and commissioning of the plant and other related components.
1.3.6 Training on
operation, maintenance and repair of the plant as well as operation of
laboratory equipment and application of analytical results, including regular
monitor the possible contamination of the environment, particularly on the
ground water at the treatment plant etc. Concerned local staff will be trained
and better aware of specific issues and problems associated with joint tannery
effluent systems to disseminate and apply the expertise gained elsewhere.
1.4 Output 4.
Establishment and operation of a solid waste
disposal system including a sanitary landfill for handling tanneries' solid
waste and dried sludge generated at the treatment plant.
An impermeable clay layer will seal the
landfill site that will be connected by a causeway to the pre-treatment plant. Over this clay layer a drain,
consisting of a series of fine to coarse material will be laid.
One bulldozer for coverage
of the (often foul smelling) sewerage regularly and five tractors, ten trailers
and five dump trucks are among those provided under the project. These vehicles
will be used for the transportation of dried sludge from the pre-treatment
plant to the landfill site as well as for solid waste collection from the
tannery clusters.
Main Activities for output 4.
1.4.1 Finalization of design dew]s, drawings
and tender documents; tendering process, evaluation and awarding etc.
1.4.2 Construction of the selected
landfill site and access road.
1.4.3 Requisition of related equipment
for compacting, collection, removal and coverage of solid and dried sludge.
1.4.4 Elaboration of a waste management
plan including a transport plan,
1.4.5 Regular monitoring of
the possible influence on the environment, particularly on the ground water at
the landfill and along the Pandoki Outfall etc.
2. Immediate objective 2
Improvement of tanners' existing inadequate
technical, managerial and environmental knowledge and skills to create a
sustainable development of tanning activities and enhance the quality of the
Rather industry, facilitating an improvement of the overall living and working
conditions of the tanners in Kasur as well as the environmental
awareness of the people at large.
2.1 Output 1.
Introduction and
demonstration of some low waste leather processing methods to be selected on
the basis of the their viability in Kasur Tannery industry such as:
- Mechanical desalting (to
reduce the amount of chlorides), affluent and in specially built wooden drums.
(The long-term target should be processing of, preferably, fresh (or chilled)
and dried hides and skins).
- Improved process control,
better general and water housekeeping (float volume, temperature and batch
rinsing).
- Recycling of floats (mainly exhausted
chrome floats).
- Use of environmentally acceptable and low
health risk chemicals (non-benzidine dyestuffs, bio-degnidable surfactant;
avoidance of PCP based biocides); avoidance of organic solvents in degreasing
and fuijshing.
- Better use and/or removal
of solid waste; protection from and collection of shavings and buffing dust;
installation of dust filters.
- Carbon dioxide deliming
me-thods in larger and mechanized tanneries.
Main activities for
output 1:
2.1.1 Re-appraisal of the
processing methods presently followed by the tanneries concerned, monitoring of
the pollution generated.
2.1.2 Selection of typical
tanneries for introduction and application of the above identified or other low
waste processing methods.
2.1.3 Demonstration of
trial batches on the basis of modified methods, tests and evaluation of the
quality of leathers produced and analysis of the effluents and wastes
discharged etc.
2.1.4 Organization of
seminars and courses designed to upgrade the knowledge of basic principles and
undemtanding of tanning process as well as practical related training
programmes to improve skills in carrying out various processes for tannery
managers, foreman an operatives.
2.1.5 Dissemination of the
most suitable and viable methods selected in the demonstration exercises for
gradual utilization in other tanneries.
2.2 Output 2.
Installation and operation
of a chrofne recovery pilot plant (possibly combined with
utilization/conversion of sofne types of solid waste) %ithin the tanning area
to dernorlstrate the possibilities of recycling of chemicals such as chrome and
conversion of tannery wastes such as fleshing into animal feed, gelatine,
tallow and other by-products of commercial value.
Main activities for output 2:
2.2.1 Review and selection of a suitable
site for the plant to be set up (it is foreseen that the site would be within
or adjacent to a medium size tannery or the project Facility-cum-Training
Centre).
2.2.2 FinAization of
detailed designs including drawings for related civil construction works and
equipment specifications.
2.2.3 Carrying out
construction works and equipment requisition; installation of equipment and
commissioning of the plant.
2.2.4 Organization of
on-the-job training programmes on plant retaliation, operation and maintenance
as well as benefits of methods like chemical recovery and by-products
conversion etc.
2.2.5 Evaluation of the
plant performance results including the economic and technical viability for
its duplication by some of the larger tanners and exploration of the
feasibility for subsequently setting up a central and common plant or several
similar individual units.
2.3 Output 3.
Development of a comprehensive package of
baseline data and measures designed to improve Umners' occupational health and
safety at works and to promote environmental awarmm of the Kasur population at
hne.
Main activities for output 3.
2.3.1 Consolidation of the baseline data
available relating to the impact of tanneries' operations on the environment
and various health risks for the workers and the town population;
2.3.2 Conducting
measurement of the micro-climate in line with WHO standards for maximum
concentration of potentially harmful and toxic agents in tanneries
2.3.3 Promotion of strict
adherence to safety at work regulations including appropriate safety measures
for macbline operators for improvement as required.
2.3.4 Dissemination of
information on chen3icals safety data (e.g. simplified safety data sheet), on
maximally adn2issible concentrations of gaseous harmful substances;
2.3.5 Preparation and
posting of signs, instruction boards an proper and safe handling of machines
and equipment; dissemination of information on chemicals safety data etc.
2.3.6 Preparation and
distribution of manuals, papers, hand-outs, videos and organization of
environmental protection oriented seminars and workshops to facilitate related
training programmes under the projects and promote the general environmental
avautness of the people at large.
3. Immediate objective 3
Creation of an enabling institutional
environment facilitating provision of improved urban services, smooth project
implementation and implementation of the 'polluters pay' principle; and
carrying out preparatory actions for the remainder of the Kasur Environmental
Improvement Programme and other social improvement actions.
3.1 Output 1.
Operational capabilities of Municipal
Committee Kasur (MCK) are Unproved to provide better urban services with
respect to solid waste, drainage desludging and sewage.
To achieve this, advisory
assistance will be provided by an all-round municipal engineer of one year,
with a thorough understanding of procedural, organizational and financial
c..-mgemert required for such irnoroveuk-nts. -1-his assistance would also
provide an input into the feasibility study for the remainder of the KEIP
components, particularly as they relate to MCK, such as the rehabilitation of
the sewage pumping station and sewerage network and the re,%mtioning of the
Rohi Nallah. It is envisaged that the advisor would be assigned to the MCK
Chairn=, but would work closely with the municipal engineering and public
health departments.
Main activities for
output 1.
3.1.1 Finalization of the
expert's job description, identification, recruitment and fielding of expert
3.1.2 A&sessment and
presentation of MCK's present capabilities, resources and operational
procedures.
3.1.3 Development of
programmes, schedules and routines including improvements thereof on the basis
of present MCK's resources.
3.1.4 Conducting revised
operational procedures and review of implementation options.
3.1.5 Preparation of a plan
for MCK's overall operational improvement including additional equipment etc.
3.1.6 Preparation of
specific municipal services and investment requirements for inclusion in the
feasibility study for the remainder of the KEIP.
3.2 Output 2.
The 1981 Outline Develoixnent Plan for Kasur
will be upgraded to an extent as to guide its urban development and prepare a
specific detailed plan for an industrial zone identified to be set up on the
freed stagnant pool area.
This work can be carried
out by the Housing and Physic4d Planning Department in association with the MCK
urban planning officer (and for the latter part in association with the Punjab
Small Scale Industries Corporation and landowners). A short-term catalytic
advisory technical assistance will be provided under the project, comprising
three short inputs of one month each (3 w/th) of a senior expatriate urban
planner.
3.3 Output 3.
Establisfunent of systems to facilitate the
application of the 'polluters pay' principle.
To facilitate the Mfiliment
of this output, the Government of Punjab will empower the KDA and KTWMA with
the necessary authority in respect to installation of water meters at every
tannery, the approval and collection of tariffs, etc. The Government of Punjab
will also empower the Deputy Commissioner of Kasur with the necessary
enforcement authority in case of non-compliance, non-participation, and payment
delinquency by existing tanneries as well as those to be established. These
actions of empowerment will be made available before start of the project.
Main activities for output 3.
3.3.1 Finalization of detailed plans
including equipment specifications, work arrangenwnts and mob I' resources
including requisition of water rrwters for installation at the tanneries.
3.3.2 Installation of water
ffwters at all water pumps of tanneries to measure the water consumption in
every tannerv as a basis for charges.
3.3.3 Finalization of
revenue control and reporting system; staff recruitment and assignment;
establishment of tariff and schedule for revenue collection by the KTWMA from
the tanners.
3.3.4 Dissemination and
undertaking of other advance preparatory activities ensuring smooth
implementation of the collection of charges.
3.3.5 Preparation of a
draft legislation for consideration of the Government of Punjab to establish a
Tannery Waste Abatement Fund and adopt a necessary mechanism making tanners in
other tanning areas within Punjab province pay for the environmental pollution
caused by their tanning activities.
3.4 Output 4.
A feasibility study for the remainder of
KEIP enabling investment and possible funding decisions.
The study should focus
especially on:
- Assmment of the needs of
the local communities and stakeholders.
- A drainage and sewerage
master plan for Kasur (storm water as well as sewage).
- The development of a
common final effluent treatment plant, which will treat both pretreated
tanneries effluent from the Unnery pre-treatment plant of the project as well
as sewage from the rest of the town.
- Support in the
finalization of the resectioning of the Rohi Nallah proposed under GOP funding;
- Rehabilitation of the
sewerage Pumping works and existing town sewers.
- A resource mobilization
strategy designed to secure appropriate grant and concessional loan financing
for the fWl completion of the programme.
The feasibility study which
would require about 10 w/m of expatriate and 10 w/m of local consultants will
be carried out under subcontracting arrangements.
Main activities for output 4.
3.4.1 Preparation of terms of reference
(TOR) for the feasibility study.
3.4.2 Review and finalization of TOR.
3.4.3 Acquisition of land for utilization in
stage 11 of KEIP,
3.4.4 Invitation and evaluation of proposals
from interested subcontract candidates, preparation of agreements, subcontract
awarding etc.
3.4.5 Monitoring of
subcontract implementation.
3.5 Output 5.
Three prefcasibility
studies namely Women in Leather Industry, Children in Leather Industry and
Health Nlonitoring in Kasur to facilitate follow-up actions by concerned
authorities and interested donors.
i) Women in Leather Industry
in Kasur
Study of women's position
in the tanneries' clusters in Kasur, with the particular objective to find
'entry points' for wonwn into the leather sector. Some topics to be studied
panicularly are the present and potential role of women in the PSIC Leather
Services Centre. Recommendations would be made regarding concrete steps to
involve wonwn in present or future leather work in Kasur, including training
programmes, demonstration centres and credit systems and to improve mother
health among the tannery workers and residents of Kasur. Tle study will also
investigate the most feasible organizational arrangements and prepare a
detailed work plan. It is envisaged that the study would require I w/m of an
expatriate sociologist and 2 w/m of a local sociologist.
ii) Children in Leather
Industry in Kasur
Child labor is often found
in Pakistan in general and also in Kasur. This study wifl investigate the
situation for children working in tanneries or in associated and related works.
Based an investigation of the magnitude of the problem, recommendations will be
made regarding possible local solutions including measures to be taken to
directly improve cud health among tannery and resident population of Kasur. It
is envisaged that the study would require I w/m of an expatriate sociologist
and 2 w/m of a local sociologist.
iij) Health monitoring in
Kawr
It is designed to prepare
for establishment of a monitoring system for health development in Kasur. This
consultancy would study the present health situation based on desk studies and
interviews with medical personnel and other resource personnel in Kasur. A
health monitoring system will be proposed in close contact and in cooperation
with the private and governznental health system. The consultancy will make a
detailed proposal, including organizational arrangements, cost estimates and
methodology to be applied. It is envisaged that I wlm of an expatriate public
health specialist would be required.
Main activities for this
output.
3.5.1 Review and
finalization of related Job descriptions for the expatriate experts and
preparation of Job descriptions for local consultants.
3.5.2 Determination of most
appropriate local counterparts directly involved in the related studies. I
3.5.3 Identification,
recruitment and fielding of experts and consultants.
3.5.4 Monitoring of the
assignments and presentation and discussion of the study findings and
recommendations including agreements on follow-up actions.
E. Project inputs.
1 Summary
The total project costs are summarized
below. The costs are based on January 1993 prices. Physical contingencies have
been included at 10% for civil works and equipment. Price contingencies have
been included at 6% per annum for local costs (civil works) and at 3.7% per
annum for foreign exchange cost (equipment) assuming that the project would be
launched during 1993 and implemented as per work plan elaborated by the end of
the Joint Formulation Mission in February of the same year envisaging tendering
of main construction works and equipment in 1994 and 1995. Conversion has been
done applying the then prevaULng rate of exchange of US$ I = Rs. 26. The PC-1
of the GOP has been approved also applying the same conversion rate of Rs.
26...equivalent to US$ 1.
Project cost in US$ '000
|
|
Drainage |
Treatment |
Sol id Waste |
In House arrangements |
Total |
|
Civil works |
2,202 |
2,462 |
223 |
228 |
5,115 |
|
Equipment* |
197 |
1,623 |
448 |
281 |
2,549 |
|
Land |
58 |
50 |
46 |
|
154 |
|
Techn. Assistance without equipment |
|
|
|
|
1,562 |
|
Total |
2,457 |
4,135 |
717 |
509 |
9,380 |
Project cost in Pakistan Rs '000
|
|
Drainage |
Treatment |
Solid Waste |
In House Arrangements |
Total |
|
Civil Works |
57,255 |
64,022 |
5,813 |
5,932 |
133,022 |
|
Equipment* |
5,122 |
42,198 |
11,648 |
7,306 |
66,274 |
|
Land |
1,500 |
1,302 |
1,188 |
|
3,990 |
|
Techn. Assistance ithout equipment |
|
|
|
|
40,612 |
|
Total |
63,877 |
107,522 18,649 13,238 243,898 |
18,649 |
13,238 |
243,898 |
* including equipment provided by UADP
In view of the time lapse and change of the
solid waste disposal site that took place after the calculations had been made,
a thorough review and updating of the budget will be made shortly after
launching the project. However it is estimated that the budget will remain
within US$ 10 million.
2. Government inputs
The Government of Pakistan
Punjab and the Government of Punjab ar@'committed to provide, as applicable:
- All inputs.required for
implementation of preparatory actions and measures as envisaged in Part
G, Prerequisites.
- All KTPCP project costs not specifically
covered by the UNDP budget of technical assistance.
|
|
Rs |
|
- Export Development Fund (EDF) |
80,000,000 |
|
- Economic Affairs Division (EAD) |
13,000,000 |
|
- Government of Punjab (GoPun) |
86,000,000 |
|
- Tanneries Association Dingarh (TAD) |
20,000,000 |
Above figures are for the whole (K7PCP)
project as designed by the Joint Formulation Mission, ie. including assistance to the Municipal Committee
(7mmediate Objective 3, urban services and Outline Development Plan,
feasibility study, on the municipal storm and sewage system, municipal waste
water wvrks; andfeasibility studies on "men and children in the
leather industry and health monitoring in Kasur).
7hey also include Rs 3.99 million
representing costs of requisition of land requiredfor the drainage, treatment, solid waste vxrks. (Details relating
to land acquisition, No-Objeciion- Certificate requirements and cost
estimates are in Annex VII)
Should the donors not
rejoin the project, foreign exchange will be needed for purchase of equipment
not provided by the UNDP.
- All costs relating to project activities
of the National Project Director (NPD): the cost of employment of the KDA and
KTWMA staff members as well as those ensuring a normal operation of the
Authority and Agency. The following Agency staff are required:
One General Manager, full
time, during project life
Other Agency staff will be
recruited in such a way that the core personnel will be recruited immediately,
additional personnel will be recruited during the project implementation, full
staffing not later than one year before the project commissioning (or before
project equipment is installed ) as per KTWMA organizational structure diagram,
Annex Vle. It specifically includes one deputy manager for operations, deputy
for finance, one plant overseer, twelve plant operators, one solid waste
overseer, two drivers, one maintenance assistant engineer, one accounting
assistant, two billing assistants and one secretary.
It is recognized that the common effluent treatment
alant (CEPTP) is actually a large andcomplex factory collecting every day about 13,000
m.m.m of heawly polluted waste water, processing it and producing a cleaner water to be discharged
into a water recipient and tens of tons of semi-solid sludge to be
disposed of at a suitable landfill.
- All costs relating to
engagement of support personnel including one full-time secretary and three
drivers required by the project office.
- All costs for the acquisition, operation
and maintenance of a project office for international and
national experts, the Authority members and Agency staff including its
associated costs such as electricity, water, installation of two
telephones and one facsimile machine, daily communication and furniture
charges, operation of UNDP provided vehicles etc. during the project
implementation.
- All cost relating to local storage,
handling and transportation of project equipment from the port of arrival to
project site.
The schedule of national inputs and
approximation of UNDP contribution is indicated in Annex VIII.
Should at some stage donors
(re)join the project they will take over part of above cost, the modalities to
be elaborated if and when the need arises.
3. UNDP inputs
All external (UNDP, other donors - the
Netherlands and NORAD) inputs to the project are assumed to be channelled to
and referred to as UNDP inputs. The Draft Terms of Reference/Job Descriptions
for Technical Assistance are elaborated in Annex IX.
The present UNDP financial inputs will be
used to cover the cost of the international and national expertise including
related supporting and monitoring activities provided within technical
assistance component of the project and of some equipment primarily for
improvement of the currently applied leather processing methods@M introduction
of low waste technologies.
Additionally, UNDP will, under TSS2
arrangement, cover the cost of technical supervision, monitoring and
backstopping services to be provided by UNIDO during project duration.
Possible inputs by the other donors will be
used to cover the cost of international and national expertise primarily
related to the social component of the project (Immediate objective 3 and its
outputs) and equipment and part of civil works needed to set up the tannery
effluent treatment plant (CEPTP).
F. Risks and safeguarding actions.
a) The most significant single project risk is that the envisaged
institutional and financial arrangements (outlined in Part B and
Schedule of Funding, Annex VM) to implement and operate the proiect will
not work. This could be caused by delays in the establishment and/or
autonomy of operations of KDAFKIVMA, delay in providing the funds as per
schedule and/or as required; inadequate management skills, poor synchronization
and interaction between various parties involved in project implementation; insufficient
experience and/or of the inadequate powers for KDA/IKTWMA, insufficient freedom
of operation for KTVMA to operate otrconunercial lines, inadequacy of KTWMA
resources or other more operational or administrative reasons.
To safeguard against this risk, it is
essemial that all preparatory actions required on the part of the Government of
Punjab including the preparation and adoption of the necessary legislation to
establish KDA, to constitute KDA, to appoint its secretary, to frame rules/bye
laws, to establish KTWMA and to appoint its general manager, and to firm up the
cost sharing agreement between GOPunjab agencies and the Tanneries Association
in a legally binding agreement have to be completed before the start of the project.
Project design further safeguards against
the above eventualities by the inclusion in the project of advisory technical
assistance for implementation.
b) A potentially serious envirorunental risk
is that of complete malfunctioning of the primaz treatment plant
during the winter season, when water levels in Sutlej river (the ultimate
recipient of the treated waste water) are reduced to a trickle (Annex X, Review
of Environinental Issues). Such a situation would force the discharge of
untreated waste water in the river body for a prolonged period, during a time
when the dilution factor is at its lowest point. Tle immediate receiving point,
a side arm of the river, normally does not have a natural flow during this
period, but is dry or comprises of stagnant water.
To safeguard against such a
situation the project includes a provision for adequate stand-by equipment and
materials to rectify any malfunctioning in the shortest possible time.
Additionally, design of the discharge channel includes valves to enable
emergency discharge in the Rohi Nallah (where it crosses the Depalpur road).
Finally, it is envisaged and insured by the Government of Punjab that Kl-WNiA
would have adequate resources to immediately implement a further emergency
solution, comprising of the bunding (through erection of earthen walls by
manual labor) of the arm of the river Sutlej down stream from where it receives
the effluent from Pandoki outfadi (effectively recreating temporary 'stagnant
pools', but in an area away from population concentration or economic
activity).
c) A potential project risk
is formed by delays in land acquisition or obtaining N.O.C.s (Part G.
Prerequisites). This can be safeguarded against by completion of the
preparatory actions required on the part of Government of Punjab in advance of
the start of project implementation.
d) A potential project risk consists of cost
escalations beyond reasonable contingency levels cannot be ruled out. To
safeguard against this risk to the best extent possible, the proiect design
provides for a detailed desigli. tender documents and cost estimates review
prior to initiation of the bidding process.
G. Prior obligations, prerequisites and
other undertakings.
a) Prior obligations and prerequisites
i) GOPunjab wfll prepare the required
legislation for the establishment of KDA, obtain concurrence from UNDP (and
possibly of other donors) and arrange for its enactment/promulgation as
an act/ordinance prior final processing of UNDP approval.
ii) Upon the enactment, GOPunjab will
constitute KDA, appoint its secretary, draft and enact its bye-laws
establishing KTWMA and, after clearance from UNDP appoint the KTWMA general
manager, prior to signing of project documents by UNDP.
iii) Appropriate office with necessary
facilities (telephone, facsimile, vehicle, parking place etc.) will be made
available in Kasur to KTWMA, core (finance, civil engineer, mechanical
engineer) and support staff employed.
The Project Manager of appropriate
background in business management and proven record in complex operations
preferably in the private sector, acceptable to UNDP, to be employed on top
urgent basis and, in any case, prior to signing the project document.
iv) GOPunjab will prepare
the project PC-1 including the necessary Goverrunent inputs and have this
approved by the competent authorities prior to signing of project document by
UNDP. GOPunjab will also provide for adequate funds in its 1995/96 ADP and
release them immediately.
v) Similarly, evidence of ability and
readiness of aH contributors (GOPunjab, EDF, TAD, GOP) to provide the funds
required as per schedule attached, Annex VHI. Also, the mechanism remedial
action to be taken in case of inability of any party to timely provide its
contribution/installment will be elaborated and provided.
It is understood that all funds will be kept
with KTWMA, regularly audited in the usuaj manner and financial situation
included into quarterly reports to the contributors and donor(s).
vi) Land for the projec-
-vill be acquired and the necessary No-Objection-Certificates (N.O.C.s) for the
right of way or . tller departments property will be obtained prior to
effectiveness of project agreements with UNDI; UNIDO (detailed land areas and
NOCs required are indicated in Annex Vil: Land for CEPTP, Dinghar and Younus
Nagar pumping stations, highway land for the Green Channel).
vii) Similarly, a suitable
landfill for disposal of solid waste resulting from operations of individual
tanneries in-plant pretreatment units from tanneries (construction of which is
one of the first project activities has to be made available before launching
the project.
viii) Concrete action to ensure power supply
needed for the drainage system and CEPTP as per existing design (approximately
500 KVA) will be initiated prior to signing of the project document to be
completed as needed according to the work plan.
ix) Prior to disbursements of project funds
by UNDP/UNIDO, GOPunjab will arrange for the conclusion of a legal agreement,
acceptable to the donor(s), embodying the depreciation and O&M cost sharing
arrangements agreed with explicit commitments by tanners and MCK/District
Council. GOPunjab will also appoint a National Project Director (NPD)
acceptable to UNDP prior to disbursement of funds.
x) All consulting and contractor services
will be obtained through open tender procedures, contracts awarded to the
technically acceptable lowest bidder to the satisfaction of UNDP. Also, the
administrative & support cost including clearing & transportation fees
at 10 % of investment cost in PC-1, Rs 19,929,000 equivalent to US$ 767,000
appear too high and should be reconsidered as it significantly affects the
overall project costs.
The Project Document will be signed by UNDP,
and UNDP assistance to the project will be provided only if the above prior
obligations and prerequisites have been fulfilled , or are likely to be
fulfilled to UNDP's satisfactions. When anticipated fulfillment of one or more
obligations and prerequisites fails to be materialized or exist, UNDP may, at
its discretion, either suspend or terminate its assistance. I
Similarly, the UNDP will, prior to
completion of Phase 1, i.e. approximately one year upon signing the project
document, based on the outcome of the review of delivery of national inputs
including, in particular, funding situation and of the actual work progress
compared against targets set take decision about its further involvement in the
project.
In case of positive outcome of that
evaluation, UNDP will provide further financing for Phase 11 of the project.
UNIDO will prepare a substantive project revision for the implementation of
Phase B, including objectives, outputs, work plans, budget, etc. The revision
will determine the date of the next review and define specific targets to be
achieved by that time. the total life of the project is estimated to be three
years and six months and UNDP's total contribution to the project including
possible cost sharing from other interested donors, is expected to amount to
US$ 2,499,800 as reflected in the attached budget (sect. J. Budgets).
b) Policy and programme undertakings
i) GOPunjab stands committed to install a
sustainable common effluent treatment plant (CEPTP) and sludge disposal
facilities and will not limit the project to mainly construction of the
drainage system and evacuation of the stagnant pools.
ii) GOPunjab stands committed to implement
the polluters pay principle as soon as is compatible with enforcement of the
EPA standards and regulations.
To give practical contents to this policy
intention, GOPunjab will actively promote similar projects and cost sharing
arrangements as agreed for the project in other tannery clusters in the
province. GOP'unjab will also initiate the establishment of a Tannery Waste
Abatement Fund. Both measures would have as objective to implement the polluters
pay principle as embodied in the project province wide and to maintain a 'level
playing' field of business conditions among the tanners in the province. It is
estimated that this can be achieved in three years time.
Once this is achieved, the Kasur Tanneries
Association has agreed to accept an increasing financial responsibility for
meeting the projft-t's O&M and depreciation costs, with their contribution
increasing every year to achieve 100% in 5 years.
iii) GOPunjab stands
committed to an early follow-up, i.e., advance land acquisition where necessary
and active pursuit of major potential donors particularly the World Bank and
the Asian Development Bank etc. Early implementation of the 2nd stage of the
Kasur Environmental Improvement Programme will enhance the cost-effectiveness
of the KTPCP plant. KTPCP includes technical assistance to make this possible.
H. Project review, reporting and
evaluation
Annex XI, Monitoring Indicators and
Arrangements provide supplementary criteria and emphasis of issues for review
and reporting activities undertaken under the project.
a) The project wfll be
subject to regular monitoring visits by UNDP officials and/or representatives
of other concerned/potential donors at least twice per year. Monitoring
missions would review progress as against the work plans, the envisaged
environmental impacts of the project and the project benefits etc, to enable
timely initiate project action to mitigate any undesirable impact or problems,
if and when these arise. It is understood that during the implementation of the
project, in order to facilitate the project operation and to achieve the
project development objectives, any adjustment required to satisfy the expected
end-,of- project situation and to ensure sustainability, will be accomodated in
consultation with the concerned parties.
b) Project Reports.
Project reports wfll be
prepared in accordance with UNDP formats for reporting. All reports are to be
submitted through KTWMB to the GOPunjab and UNDP, who will in turn distribute
to other concerned donor and parties.
The National Project Director (NPD) will
prepare, in consultation with the CTA, brief quarterly and detafled semi-annual
performance reports. Project performance reports wfli provide information on
activities and outputs compared to project work plans and will highlight major
problem areas, with suggestions for overcoming them.
The project wfll be subject to joint review
by members of the Steering Committee and representative of UNM at least every
12 months. The Project Performance Evaluation Reports (PPER) in UNDP formats
which wfll replace the second semiannual performance reports will be prepared
by the NPD in consultation with the UNDP Programme Officer. PPERs will be made
available one month before the annual joint review meeting date. In preparation
of the PPER, the project will undertake internal evaluations of all operational
matters relating to the project implementation and prepare suggestions for revisions and
project design if necessary to be incorporated into the PPER. The initiation of
internal evaluations is the responsibility of the project management.
Two month before the end of the project a
Final Project Report will be prepared by NPD in consultation with the
Progranune Officer and UNIDO.
c)Evaluation.
The project shafl be
subject to an independent in-depth evaluation before the end of the project preferably right after the commissioning of the
project treatment plant. Detailed tern-is of reference,
team composition and main methods to be applied to satisfy different evaluation
needs of all the concerned donor(s), GOP and UNIDO will be prepared by UNDP and have it agreed in
advance.
Also, as already mentioned in the last paragraph
of Part G., UNDP/TJNIDO prior to completion of Phase 1, i.e. approximately one
year upon signing the project document, will review the funding situation and
work progress compared against targets determined and make a decision about
further involvement in the project.
I. Legal context
This Project Document shall be the instrument
envisaged in the supplemental provisions of the PPM, section 30503.
The Govemment agrees to the
recruitment of nationally recruited professional project personnel (NPPP)
required for the implementation of this project, in accordance with UNDP
policies and procedures established within the United Nations system for this
purpose. These services constitute an addition to the regular person resources
to be provided by the Government and will be available for the duration of the
UNDP participation in the project. Tne remuneration of the NPPP will be
determined on a case by case basis in accordance with the policies and
procedures of UNDP; it should exceed neither the prevailing compensation for
comparable functions in the host country nor remuneration level applicable
within the United Nations system.
All nationals employed
locally and financed by UNDP to perform professional services under this
project shall be accorded:
(a) Immunity from legal process of any kind
in respect of words spoken or written and acts done in the cause of the
performance of their duties;
(b) Inviolability of afl papers and
documents connected with his or her duties; and
(c) For the purpose of his or her
communications with the UNDP, the right to receive papers and correspondence by
courier or in sealed bags.
The following types of
revisions may be made to this project document with the signature of the UNDP
Resident Representative only, provided he or she is assured that the other
signatories of the project document have no objections to the proposed changes:
(a) Revisions in, or addition of, any of the
annexes of the project document, with the exception of the standard legal text
for non-SBAA countries which may not be altered and the agreement to which is a
pre-condition for UNDP assistance;
(b) Revisions which do not
involve significant changes in the immediate objectives, outputs or activities
of a project, but are caused by the rearrangement of inputs already agreed to
or by cost increases due to inflation; and
(c) Nlandatory annual revisions which
re-phase the delivery of agreed project inputs or increased expert or other
costs due to inflation or take into account agency expenditure flexibility.
J. Budgets
See attached budget sheets of UNDP technical
assistance for Phase I and the tentative budget for Phase fl which will be
elaborated, in detail, upon project evaluation exercises to be carried out
before completion of phase I
****************************************************************************************
Go
Back to the Main Page of Pakistan Society of Geographic Information Systems
(PSGIS)
Contact for further information
Participatory Development Resource Cell
(PDRC),
Sakano - Lab,
Tokyo Institute of Technology, JAPAN